  • Job Duration: 12 Months
  • Client: Daktronics

The Mission

Installation of 2 27m x 10m LED video playback screens on either end of the stadium

Installation of pitch perimeter and on field Led video screens totaling 370m

installation of parapet LED video screens totaling 1126m

Challenges

All tasks were completed during the construction of the stadium and had to be planned around the enormous amount of personnel and other plant onsite and conform to a very demanding installation schedule